On December 20, 2020, the first batch of 4
piperack modules (U001, U002, U003, U004) in AP N2 GASUNIE project was
successfully completed and shipped from Yanda jetty.
Max length of four piperack modules in first batch is 40m. The materials are stainless steel and carbon steel with bolted connection, and total weight is 320T. AP N2 GASUNIE Project site is located in Zuidbroek, the Netherlands, and will be used to provide an air separation plant for nitrogen.
With multiple challenges such as tight project schedules, numerous design revisions and epidemics, Yanda Haimen insisted on keeping the project delivery time unchanged as the goal. According to the characteristics of the project, the project team carried out detailed planning and serious preparations in the early stage, and worked closely with various departments. Project team strictly controlled the plan, and worked hard for days to complete the construction and delivery of the first batch with 4 piperack modules. The safety, quality, schedule and on-time delivery of the project have been awarded and recognized by AP and the owner.
Copyright © yanda 2020 | All Right Reserved.